Cornerstone Sanitary Lift Station

Construction Projects

Project Overview

  • Project: Cornerstone Sanitary Lift Station
  • Location: Calgary, Alberta
  • Timeline: October 2024 – December 2025
  • Delivery Method: Design-Build
  • Project Type: Wastewater Lift Station (Cast-in-Place Concrete Wet Well)

The Challenge

The Cornerstone Sanitary Lift Station required aggressive schedule delivery on a site with significant technical challenges:

  • Deep excavation (~50 feet) with complex dewatering requirements
  • Winter construction requiring temperature-controlled concrete pours
  • Cast-in-place concrete wet well constructed through challenging weather conditions
  • Concurrent construction with the Cornerstone Storm & Irrigation Lift Station 
  • Proximity to residential development requiring architectural finishes and minimal disruption

The owner needed a fully operational lift station delivered on schedule despite weather constraints and site complexity.

Key Project Features

Cast-in-Place Concrete Wet Well

  • Deep excavation (~50 feet) with complex dewatering and shoring
  • Winter concrete pours with heating and temperature control
  • Durable, long-term wet well construction for municipal-grade performance

Prefabricated Building 

  • Off-site fabrication while underground work progressed
  • High-quality finishes suitable for proximity to residential development
  • Faster on-site assembly and commissioning

Process Piping and Mechanical Systems

  • Self-performed mechanical scope for quality control
  • Prefabricated piping assemblies for faster installation
  • Integration with force mains and gravity sewers

Electrical and Control Systems

  • Advanced control panels for automated operation
  • Level control, pump sequencing, and alarm systems
  • Remote monitoring capability for long-term operations

Our Approach

Design-Build Collaboration

We worked to establish flow parameters, capacity requirements, and site constraints. Our design optimized wet well sizing, pump selection, and system configuration to meet long-term performance requirements while supporting an aggressive construction timeline.

Prefabrication for Speed and Quality

We prefabricated the building off-site in our shop while underground work progressed. This approach allowed us to:

  • Work on fabrication and site construction simultaneously without interference
  • Improve quality control in a controlled shop environment
  • Reduce on-site assembly time and weather-related delays
  • Meet the aggressive schedule despite winter construction challenges

Self-Performed Scope

Systems Group Inc. self-performed mechanical, structural, and process piping work, giving us direct control over quality, schedule, and problem-solving throughout the winter construction period.

Project Highlights

"We were able to accomplish the owner's schedule despite very challenging winter conditions and a deep, complex excavation. Prefabricating the building off-site while underground work progressed allowed us to double up activities and meet the aggressive timeline."

— Trevor Sigfusson, Principal, Systems Group Inc.